Free PK0-004 Exam Braindumps (page: 14)

Page 14 of 182

Which of the following documents should be used to provide high-level reporting to key stakeholders?

  1. Dashboard
  2. Communication plan
  3. Statement of work
  4. Project charter

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 325



A new project charter is being drafted.
Which of the following would be the BEST source for the high-level project requirements?

  1. Sponsor
  2. Project manager
  3. Project management office
  4. Project team

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 108



Which of the following project documents should be used to record the occurrence of an unplanned event?

  1. Action log
  2. Risk log
  3. Change log
  4. Issue log

Answer(s): D


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 327



Which of the following documents does a vendor rely on MOST before committing funding and resources to a project?

  1. SOW
  2. PO
  3. SLA
  4. MOU

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299






Post your Comments and Discuss CompTIA PK0-004 exam prep with other Community members:

PK0-004 Exam Discussions & Posts