Which of the following measurements would give the project manager the BEST estimate of the total cost of an active project?

  1. EAC
  2. BAC
  3. TCPI
  4. ETC

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 232



A customer will have ongoing changes to project requirements.
Which of the following is the BEST project management methodology for this requirement?

  1. Waterfall
  2. Agile
  3. PRINCE2
  4. Bottom-up

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 310



Which of the following describes risk mitigation?

  1. The transfer of the risk to another entity or project inside or outside the organization, along with associated costs.
  2. The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.
  3. The quantification of the risk in terms of how much the risk could potentially cost the project or parent organization.
  4. The weighting or prioritization of the risk against all other identified risks within this project or others associated with it.

Answer(s): B



Which of the following is a definition of an RFP?

  1. A document sent to potential vendors to solicit a bid for a project.
  2. A document sent to potential vendors to request information for skills and experience for a project.
  3. A document sent to potential vendors to request a commitment for a project.
  4. A document sent to potential vendors to solicit information that excludes pricing information for a project.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 300