CompTIA PK0-004 Exam Questions
CompTIA Project+ (Page 15 )

Updated On: 16-Feb-2026

A project team is mainly based in a metropolitan area. The team also has members in a remote area, where Internet access is limited and unstable.

Which of the following factors will MOST likely influence the communication methods used in the project?

  1. Personal preferences
  2. Technological factors
  3. Language barriers
  4. Cultural differences

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 270



A project manager noticed the development team supporting a project does not have sufficient skills to complete the development phase. The project manager has discussed this issue with the functional manager and agreed to continue with the development phase due to time restrictions.
Which of the following strategies is the project manager applying?

  1. Accepting
  2. Mitigating
  3. Avoiding
  4. Transferring

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 238



A business has implemented a new online performance management tool that allows functional and project managers to rate employees online. This action is known as which of the following?

  1. Business process change
  2. Organizational change
  3. Internal reorganization
  4. Business continuity planning

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 297



A project manager needs to track the actual and estimated start and finish dates of all WBS work packages. Which of the following is a necessary step to record the actual durations?

  1. Establish each WBS work package resource.
  2. Establish and set the baseline.
  3. Establish and set the quality gates.
  4. Establish the tollgates.

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 167



Which of the following describes how a project is related to a program?

  1. A program is a combination of multiple projects.
  2. A program contains an element of the project.
  3. A program is a part of a project.
  4. A program uses half of the project’s budget.

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 72