CompTIA PK0-004 Exam Questions
CompTIA Project+ (Page 22 )

Updated On: 17-Feb-2026

A project’s key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)

  1. Cost performance parameter
  2. Project schedule
  3. KPI
  4. Corrective action plan
  5. WBS

Answer(s): B,E


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 133 https://books.google.co.za/books?id=evR0gPFBHJ4C&pg=PA128&lpg=PA128&dq=complete+a+project
+sooner+-+update+WBS&source=bl&ots=O650UKpUEK&sig=mlexbBmFJKkAuXuftqO2YjLLOgo&hl=en&sa=X&ved=0ahUKEwi8uJXIj_DXAhUKuRQKHW3fDKAQ6AEIMTAC#v=onepage&q=complete%20a%20project%20sooner%20-%20update%20WBS&f=false



A project has activities on the critical path that must be completed before other activities can start.

Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.

Which of the following is the appropriate ordering of the critical path?

  1. B, A, D
  2. C, B, D, A
  3. D, A, C
  4. B, C, A, D

Answer(s): D



During a project, the project manager discovers there is insufficient time allotted for quality control. The project manager prepared to submit a revised schedule to the CCB.


Given the attached chart, which of the following is the critical path if one day is added to each task for quality control?

  1. 12 days
  2. 16 days
  3. 17 days
  4. 22 days

Answer(s): D



Which of the following job roles is primarily tasked with communicating the project timeline changes?

  1. Project scheduler
  2. Project manager
  3. Project sponsor
  4. Project coordinator

Answer(s): B


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 93



A project manager is successfully adhering to an eight-week project schedule through week three. A change in the marketplace will require the project manager to deliver the product one week early.


Given the project schedule above, which of the following aspects are missing for the project manager to plan and execute an accelerated schedule? (Choose two).

  1. Cost
  2. Predecessors
  3. Lag
  4. Durations
  5. Resource loading
  6. Subtasks
  7. Float

Answer(s): A,E