A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.
The project manager is concerned that the requests will lead to:

  1. quality control issues.
  2. additional risks.
  3. scope creep.
  4. time constraints.

Answer(s): C



A vendor has accepted a proposed project from a customer.
Which of the following is MOST likely to be the first document created by the project manager?

  1. Project charter
  2. Project management plan
  3. Project statement of work
  4. Project schedule

Answer(s): C


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 299



A project manager has noticed poor attendance as status meetings.
Which of the following strategies should the project manager use to improve attendance? (Choose two.)

  1. Provide an agenda before the status meeting.
  2. Adhere to an agenda and scheduled time.
  3. Add non-project-related items to the agenda.
  4. Add and discuss new agenda items throughout the meeting.
  5. Discard the action items at the conclusion of the meeting.

Answer(s): A,B



Which of the following events would MOST likely trigger communications to the largest audience for a given organization?

  1. Business continuity response
  2. Quality audit
  3. Replacement of a subcontractor
  4. Completion of a task

Answer(s): A


Reference:

Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 273



Viewing page 23 of 182
Viewing questions 89 - 92 out of 1001 questions



Post your Comments and Discuss CompTIA PK0-004 exam prep with other Community members:

PK0-004 Exam Discussions & Posts