A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?

  1. Multiauthoring software Most Voted
  2. Word processor
  3. Real-time polling
  4. Conferencing platforms

Answer(s): A



The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

  1. External
  2. Internal
  3. Mandatory Most Voted
  4. Discretionary

Answer(s): C



A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?

  1. Issue log
  2. Gantt chart
  3. Milestone chart
  4. Change control log

Answer(s): A



Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?

  1. Project change management plan
  2. Project management plan
  3. Project transition plan
  4. Project communication plan

Answer(s): B



Page 5 of 53



Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:

Jack commented on October 18, 2024
are these legit ?
Anonymous
upvote

samsam commented on September 11, 2024
i hope this will help me pass
Anonymous
upvote

Joe commented on March 26, 2024
it helped me pass
Anonymous
upvote