A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
Answer(s): A
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
Answer(s): C
A hurricane delays the shipment of critical equipment for a project. Which of the following is BEST to use to document the effects of this delay?
Due to budgetary and time constraints, a PM scheduled a meeting with all stakeholders during the planning phase to review the requirements and come to an agreement on the minimum viable product that would be acceptable. Which of the following would be used to document this input?
Answer(s): B
Post your Comments and Discuss CompTIA PK0-005 exam with other Community members:
Jack commented on October 18, 2024 are these legit ? Anonymous upvote
samsam commented on September 11, 2024 i hope this will help me pass Anonymous upvote
Joe commented on March 26, 2024 it helped me pass Anonymous upvote