Which tool or technique used in the Control Procurements process can be conducted during the execution of the project to verify compliance with deliverables?

  1. Procurement documents
  2. Inspection and audits
  3. Estimate budget
  4. Risk register

Answer(s): B



An example of a group decision-making technique is:

  1. nominal group technique
  2. majority
  3. affinity diagram
  4. multi-criteria decision analysis

Answer(s): B



Which type of graphic is displayed below?

  1. Work breakdown structure
  2. Context diagram
  3. Control chart
  4. Pareto diagram

Answer(s): A



The zero duration of milestones in project planning occurs because milestones:

  1. Are unpredictable and challenge the Plan Schedule Management process.
  2. Occur at random times in the project plans.
  3. Represent a moment in time such as a significant project point or event.
  4. Represent both significant and insignificant points in the project and are difficult to anticipate.

Answer(s): C



The degree of uncertainty an entity is willing to take on in anticipation of a reward is known as its risk:

  1. management
  2. response
  3. tolerance
  4. appetite

Answer(s): D