Which is an enterprise environmental factor?

  1. Marketplace conditions
  2. Policies and procedures
  3. Project files from previous projects
  4. Lessons learned from previous projects

Answer(s): A



Project Stakeholder Management focuses on:

  1. project staff assignments
  2. project tea m acquisition
  3. managing conflicting interests
  4. communication methods

Answer(s): C



A risk that arises as a direct result of implementing a risk response is called a:

  1. contingent risk
  2. residual risk
  3. potential risk
  4. secondary risk

Answer(s): D



The purpose of developing a project scope management plan is to:

  1. Manage the timely completion of the project.
  2. Ensure that the project includes all of the work required.
  3. Make sure the project will satisfy the needs for which it was begun.
  4. Reduce the risk of negative events in the project.

Answer(s): B