An output of Control Schedule is:

  1. A project schedule network diagram
  2. A schedule management plan
  3. Schedule data
  4. Schedule forecasts

Answer(s): D



What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?

  1. Failure modes and effects analysis
  2. Design of experiments
  3. Quality checklist
  4. Risk analysis

Answer(s): B



Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?

  1. Build vs. buy
  2. Expert judgment
  3. Alternatives identification
  4. Product analysis

Answer(s): C



Most experienced project managers know that:

  1. every project requires the use of all processes in the PMBOK® Guide.
  2. there is no single way to manage a project.
  3. project management techniques are risk free.
  4. there is only one way to manage projects successfully.

Answer(s): B



What is an objective of the Develop Project Team process?

  1. Feelings of trust and improved cohesiveness
  2. Ground rules for interaction
  3. Enhanced resource availability
  4. Functional managers becoming more involved

Answer(s): A