A bank is designing an on-the-job training program for its branch managers. The bank would like to design the program so that participants can complete it as quickly as possible. The training program requires that certain activities be completed before others. For example, a participant cannot make credit loan decisions without first having obtained experience in the loan department. An appropriate scheduling technique for this training program is:
- PERT/CPM.
- Linear programming.
- Queuing theory.
- Sensitivity analysis.
Answer(s): A
Explanation:
PERT/CPM is a network technique for scheduling interrelated time series activities and identifying any critical paths in the series of activities The critical path is the longest path through the network.