In the Gantt chart below, shaded bars represent completed portions of activities, bars depicted with broken lines represent uncompleted portions, and blank bars represent activities notyet begun.
As of week 8, the Gantt chart shows that the project is:
- Complete.
- Ahead of schedule.
- On schedule.
- Behind schedule.
Answer(s): C
Explanation:
Activities B and C are the only activities that should be underway during week 8. Since both are underway and on schedule, the project is on schedule.