When a business analyst is using alternative generation, what should she always include as an output?
Answer(s): C
Whenever generating alternatives, the business analyst should always include the option of doing nothing. Answer A is incorrect. The best answer is to include the option of doing nothing; the cost of the requirements isn't an in-depth consideration at this point.Answer B is incorrect. The schedule for the implementation is often considered, but the option of doing nothing should always be considered.Answer D is incorrect. The cost of each solution isn't the best choice for this Question.
You are the business analyst in your organization and you're working to organize the requirements for the business units in your company. Which technique is best suited for structuring requirements around the needs of each stakeholder group?
Answer(s): A
Organizational modeling is the best choice, as this structuring approach allows requirements to be structured around organizational units, stakeholders, and the relationships among stakeholders. Answer C is incorrect. Data modeling isn't the best choice, as this approach maps the concepts relevant to the business domain, not the business units. Answer D is incorrect. Functional decomposition is a popular modeling approach that breaks down an organization, product, scope, or similar concept. Each part in the decomposition can have its own set of requirements.Answer B is incorrect. User stories describe the stakeholder objectives that the solution will support.
There are four methods to generate the business need in an organization. Which approach is described as the need to achieve a strategic goal?
From the top down is described as the need to achieve a strategic goal. Answer A is incorrect. From the bottom up is described as a problem with the current state of a process, function, or system.Answer D is incorrect. From middle management is described as a manager needs additional information to make sound decisions or must perform additional functions to meet business objectives.Answer B is incorrect. From external drivers is used when there's recognized competition in the marketplace.
You are the business analyst for your organization and you're training Marcy, a new business analyst, on how requirements are defined. Which one of the following best describes how requirements are defined?
Requirements are based on stakeholders' needs, wants, and expectations. This is why it's important to identify stakeholders and requirements gathering processes early in the project to quickly and accurately capture requirements.Answer D is incorrect. This is not a valid answer to the question as not all requirements gathering are solutions-driven, but could be just a study.Answer B is incorrect. The risk and reward solution is always considered, but requirements are based on stakeholders' needs, wants, and expectations.Answer C is incorrect. The change-driven approach isn't a valid answer for this Question.
Complete this sentence in regard to the level of abstraction. Requirements need to say needs to be done, not to do it.
Requirements need to say what needs to be done, not how to do it. Answer A is incorrect. This isn't a valid statement about the level of abstraction, as the schedule isn't addressed.Answer B is incorrect. This isn't a valid statement about the level of abstraction, as the resources and project team aren't addressed.Answer D is incorrect. This isn't a valid statement about the level of abstraction, as the cost of the requirements is not addressed.