A project manager and team from a firm that designs railroad equipment are tasked to design a machine to load stone onto railroad cars. The design allows for two percent spillage, amounting to over two tons of spilled rock per day.
In which of the following does the project manager document quality control, quality assurance, and quality improvements for this project?

  1. Quality management plan
  2. Quality policy
  3. Control charts
  4. Project management plan

Answer(s): A



All of the following are inputs to the quality process EXCEPT:

  1. Organizational process assets.
  2. Checklists.
  3. Quality policy.
  4. The project scope statement.

Answer(s): B



A quality management plan is created during which of the following?

  1. Project Executing
  2. Plan Quality
  3. Perform Quality Assurance
  4. Perform Quality Control

Answer(s): B



Which of the following is an example of a tool used in Plan Quality?

  1. Fishbone diagram
  2. Quality audit
  3. Cause and effect diagram
  4. Benchmarking

Answer(s): D