If two events cannot both occur in a single trial, they are:

  1. False events.
  2. Mutually exclusive.
  3. Statistically independent.
  4. Just-in-time.

Answer(s): B



The customer's expectations for quality are shown on a control chart as the:

  1. Mean.
  2. Specification limits.
  3. Rule of seven.
  4. Upper and lower control limits.

Answer(s): B



Co-location can help with:

  1. Bringing customers together.
  2. Building the team.
  3. Decreasing project rental costs.
  4. Decreasing project time.

Answer(s): B



A project involves arranging for the closing of the company office where the team works and relocating everyone to a new city. The BEST thing the project manager can do is:

  1. Spend time carefully creating the work breakdown structure.
  2. Have a strong quality control plan.
  3. Decrease the fringe benefits.
  4. Carefully consider the reward system for the project.

Answer(s): D