The seller tells you that your activities have resulted in an increase in their costs. You should:

  1. Recommend a change to the project costs.
  2. Have a meeting with management to find out what to do.
  3. Ask the seller for supporting information.
  4. Deny any wrongdoing.

Answer(s): C



Which of the following is CORRECT?

  1. The critical path helps prove how long the project will take.
  2. There can be only one critical path.
  3. The network diagram will change every time the end date changes.
  4. A project can never have negative float.

Answer(s): A



Which of the following is CORRECT about quality improvements?

  1. They are a tool of Perform Quality Assurance and an output of Verify Scope.
  2. They require the preparation of change requests or the recommendation of corrective actions.
  3. They occur only through experience of the project manager, team, and sponsor.
  4. They are a product of cooperation between the customer and the project manager.

Answer(s): B



A problem occurs on an activity with free float and the project manager has extended its duration.
What is MOST likely to be affected?

  1. Project duration
  2. Resource schedules
  3. Project scope management plan
  4. The latest start for the successor activity

Answer(s): B