ITIL ISEB-PM1 Exam
ISEB-PM1 Foundation Certificate in Project Management (Page 24 )

Updated On: 12-Feb-2026

Which of the following is not true for a Responsibility Assignment Matrix (RAM)?

  1. Defines what project member is responsible for each activity
  2. Defines all people associated with each activity
  3. Defines responsibilities for each WBS component
  4. All of the other alternatives apply

Answer(s): D



Giving a part of project work to a contractor is an example of:

  1. risk assumption
  2. risk assignment
  3. risk delegation
  4. risk deflection
  5. risk mitigation

Answer(s): D



Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6 days, what is the PERT weighted average?

  1. 6.1
  2. 6.3
  3. 6
  4. 4

Answer(s): C



Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.

  1. Increase, increase.
  2. Increase, decrease.
  3. Remain the same, return to customer.
  4. Decrease, increase.
  5. Decrease, decrease.

Answer(s): C



The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project manager probably have the easiest time in integrating work?

  1. Matrix
  2. Pure project
  3. Coordinator
  4. Classical
  5. Expediter

Answer(s): B






Post your Comments and Discuss ITIL ISEB-PM1 exam prep with other Community members:

Join the ISEB-PM1 Discussion