In which project management process is the detailed project budget created?

  1. Initiating.
  2. Closure.
  3. Planning.
  4. Executing.

Answer(s): C



Decomposing the major deliverables into smaller, more manageable components to provide better control is called:

  1. scope planning.
  2. scope definition.
  3. scope baselining.
  4. scope verification.

Answer(s): B



If the project has accepted the suppIier's work and updated the progress tracking tool, what is the next step fora project which is not using real time interface version 4 (RTI 4.0)?

  1. Cost & progress manager updates SAP with the billing block release date.
  2. Cost & progress manager updates SAP with the goods receipt date.
  3. Logistics coordinator updates SAP with the billing block release date.
  4. Logistics coordinator updates SAP with the goods receipt date.

Answer(s): D



What is the purpose of the post project review?

  1. To review of how a contract is performing against the customer and LoA commitments.
  2. To communicate the project closure and to collect and communicate lessons learned and best practices.
  3. To formally conclude all project actMties including ramping down of resources, closing the project in the financial tools, and archMng project documentation.
  4. To provide an overview of the project performance and to identify gaps related to planning and preparation work.

Answer(s): B



What are the two key elements to calculate the project cost adherence (PCA)?

  1. Cost overrun of the period and total costs of sales of the period.
  2. Estimate at completion and cost baseline.
  3. Actual costs and the latest estimate in PRS.
  4. Estimated baseline and cost baseline.

Answer(s): B