CPM Questions 61–65 (page: 14)

Updated On: 9-Feb-2026

The ________________ is not a part of the project base costs but is included in the project budget:

  1. actMty cost contingency reserve.
  2. risk contingency reserve.
  3. management overheads.
  4. project management planning.

Answer(s): B



When should a risk be avoided?

  1. When the risk event has a low probability of occurrence and low impact.
  2. When the risk event is unacceptable, generally one with a very high probability of occurrence and high impact.
  3. When it can be transferred by purchasing insurance.
  4. A risk event can never be avoided.

Answer(s): B



Which of the following is NOT part of the IPM suite?

  1. Sales management.
  2. Site data management.
  3. Change management.
  4. Document management.

Answer(s): A



Your project is ongoing. All partner contracts have been renegotiated and new prices (higher by 8%) came into effect immediately. If all the other circumstances in your project remain unchanged, your ETC value will:

  1. Increase by 8%.
  2. Increase by a certain % dependent on other project costs in ETC.
  3. Decrease by 8%.
  4. Decrease by a certain % dependent on other project costs in ETC.

Answer(s): B



When should the costs be recognized when utilizing IPM as part of the site process for a customer project?

  1. When internal acceptance is granted.
  2. When the invoice from the subcontractoris received.
  3. When the purchase order is created and sent to the subcontractor.
  4. When the subcontractor confirms receipt of the purchase order.

Answer(s): A