Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

  1. Estimate Costs
  2. Estimate Activity Resources
  3. Control Costs
  4. Determine Budget

Answer(s): D

Explanation:

Process: 7.3 Determine Budget
Definition: The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.
Key Benefit: The key benefit of this process is that it determines the cost baseline against which project performance can be monitored and controlled.
Inputs
1. Cost management plan
2. Scope baseline
3. Activity cost estimates
4. Basis of estimates
5. Project schedule
6. Resource calendars
7. Risk register
8. Agreements
9. Organizational process assets

Tools & Techniques
1. Cost aggregation
2. Reserve analysis
3. Expert judgment
4. Historical relationships
5. Funding limit reconciliation

Outputs
1. Cost baseline
2. Project funding requirements
3. Project documents updates



Plan Risk Management is the process of defining how to:

  1. Communicate identified risks to the project stakeholders.
  2. Conduct risk management activities for a project.
  3. Analyze the impact a specific risk may have on the project.
  4. Address unexpected risks that may occur during a project.

Answer(s): B

Explanation:

Process: 11.1 Plan Risk Management
Definition: The process of defining how to conduct risk management activities for a project.
Key Benefit: The key benefit of this process is it ensures that the degree, type, and visibility of risk management are commensurate with both the risks and the importance of the project to the organization. The risk management plan is vital to communicate with and obtain agreement and support from all stakeholders to ensure the risk management process is supported and performed effectively over the project life cycle.

Inputs
1. Project management plan

2. Project charter
3. Stakeholder register
4. Enterprise environmental factors
5. Organizational process assets

Tools & Techniques
1. Analytical techniques
2. Expert judgment
3. Meetings

Outputs
1. Risk management plan



If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

  1. One
  2. Five
  3. Six
  4. Seven

Answer(s): C

Explanation:

E = (a + 4m + b) / 6
(2+ (4*5) +14)=36 /6 =6



The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?

  1. US$158,700
  2. US$172,500
  3. US$187,500
  4. US$245,600

Answer(s): C

Explanation:

CPI = budgeted cost of work performed (BCWP) / actual cost of work performed (ACWP) US$172,500 / US$187,500 = 0.92



Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

  1. Control chart
  2. Earned value
  3. Variance
  4. Trend

Answer(s): D

Explanation:

6.7.2.1 Performance Reviews
Performance reviews measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress. Various techniques may be used, among them:
Trend analysis. Trend analysis examines project performance over time to determine whether performance is improving or deteriorating. Graphical analysis techniques are valuable for understanding performance to date and for comparison to future performance goals in the form of completion dates.
Critical path method (Section 6.6.2.2). Comparing the progress along the critical path can help determine schedule status. The variance on the critical path will have a direct impact on the project end date. Evaluating the progress of activities on near critical paths can identify schedule risk.
Critical chain method (Section 6.6.2.3). Comparing the amount of buffer remaining to the amount of buffer needed to protect the delivery date can help determine schedule status. The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate.
Earned value management (Section 7.4.2.1). Schedule performance measurements such as schedule variance (SV) and schedule performance index (SPI), are used to assess the magnitude of variation to the original schedule baseline. The total float and early finish variances are also essential planning components to evaluate project time performance. Important aspects of schedule control include determining the cause and degree of variance relative to the schedule baseline (Section 6.6.3.1), estimating the implications of those variances for future work to completion, and deciding whether corrective or preventive action is required. For example, a major delay on any activity not on the critical path may have little effect on the overall project schedule, while a much shorter delay on a critical or near-critical activity may require immediate action. For projects not using earned value management, similar variance analysis can be performed by comparing planned activity start or finish dates against actual start or finish dates to identify variances between the schedule baseline and actual project performance. Further analysis can be performed to determine the cause and degree of variance relative to the schedule baseline and any corrective or preventative actions needed.