An agile practitioner wants to communicate the effect of technical debt on the project.
What should the practitioner do?

  1. Post and discuss rises in the burn down chart
  2. Adjust story points to account for technical debt
  3. Log technical debt as an impediment
  4. Add refactoring tasks to all stories

Answer(s): C



An agile coach realizes that a team responsible for a major release is a few months behind schedule. The marketing department is unaware of this delay, and is planning to start the marketing campaign and announce the release.
What should the agile coach do?

  1. Meet with the agile team lead to discuss ways to improve the team velocity and get back on track
  2. Use this as a learning opportunity and allow the team to handle the situation when the marketing campaign begins
  3. In the upcoming retrospective, discuss ways to improve sharing project status information
  4. Meet with the marketing stakeholders to explain that the team will miss the planned release date

Answer(s): C



The product owner of an agile project is frustrated because the team is unable to deliver as many features as expected. The product owner asks the team to reduce test-automation levels, since the quality assurance team will test the product at project completion. The product owner expects that more features will be delivered in each iteration using this approach.
What should the agile practitioner do?

  1. Ask the opinion of key stakeholders and the client to ensure the correct approach is being used
  2. Work with the team to use this approach, and request a quality assurance iteration after every three iterations
  3. Propose to completely eliminate test automation, since this is a quality assurance function
  4. Suggest merging the quality assurance and delivery teams to enhance each iteration's test-automation levels and redundancy

Answer(s): D



How can an agile practitioner ensure that all key stakeholders are properly engaged in planning?

  1. Collect stakeholder requirements
  2. Conduct an iteration planning meeting
  3. Communicate product backlog items to the stakeholders
  4. Facilitate a product development roadmap workshop

Answer(s): D



Page 5 of 81



Post your Comments and Discuss PMI PMI-ACP exam with other Community members:

mustapha commented on August 14, 2024
good simulation
Anonymous
upvote

Ravi commented on March 28, 2024
I am from India. I wrote this exam last week and I passed. The study material is good. Saved me a lot of time. I was actually planning on a bootcamp but then I came across this site and decided to give a try. It worked out well.
INDIA
upvote

Krasen commented on June 15, 2023
Thank you for these questions and answers. The 50% discount code worked. I bouth 2 exams and I already passed one.
HONG KONG
upvote

Adam K commented on May 24, 2023
The stuff is really good. I do recommend it.
POLAND
upvote

Herath commented on March 18, 2022
I am happy to report that I passed my second exam today. Thank you guys for this helpful study package.
SINGAPORE
upvote

BBQ commented on December 30, 2021
It is a very useful information before going to your actual exam.
HONG KONG
upvote

Kristopher commented on January 27, 2019
I loved the payment part of the website. They do not ask for any personal information. Just the credit card number and date. Very desecrate. I like!
UNITED KINGDOM
upvote

Ivan Cheung commented on August 23, 2016
The material is useful and save me a lot of time to get the exam passed without any difficulty!!
HONG KONG
upvote