An Agile team is under pressure to deliver an application. The product owner anticipates many change requests from customers once the product is released.
What should the agile team do?

  1. Demand frequent product reviews by the product owner
  2. Continuously work with the product owner to do backlog refinement and product reviews
  3. Have the product owner provide detailed requirement specifications to ensure the proper features are delivered
  4. During the planning session, ensure the team is committed to deliver within the specifications

Answer(s): B



During iteration planning, it was determined that an epic should be decomposed.
What was the determining factor?

  1. Size and priority
  2. Minimum marketable features
  3. Release plan
  4. Sprint mapping

Answer(s): A



What should a scrum master do when one team member falls behind in their tasks?

  1. Move the task to another team member who has spare capacity in the sprint
  2. Ask the team for suggestions
  3. Privately offer the team member encouragement to meet task commitments
  4. Notify the product owner

Answer(s): B



A newly formed scrum team wants to foster an environment for transparency and experimentation. The team decides to use a Kanban board to record and track encountered impediments. Emphasis is placed on how issues are resolved and the strategies for preventing them in the future.
Over time, what will be the result of this approach?

  1. Kaizen
  2. Specific, measurable, assignable, realistic, and time-based (SMART) goals
  3. Key performance indicators (KPIs)
  4. Muda

Answer(s): A