An agile team identifies that their velocity is lower than predicted, and that their previous forecasts in the product roadmap are wrong. The team is worried that they will be unable to meet a critical release date without corrective action.What should the team do?
Answer(s): D
A product owner adds a 21-point, high-priority story to a sprint backlog. The team is concerned that it cannot be completed during the current sprint.What should the team do?
Answer(s): C
A senior team member feels underutilized.What should the agile practitioner do?
A product that recently went to market is receiving a great deal of attention from upper management who expresses interest by directly emailing and calling the developer team. The team expresses frustration during a standup.What should the Scrum Master do?
Answer(s): A
What estimation technique is an agile team using when collectively estimating the relative size of its stories using story points?