A project manager has been appointed to a multimillion-dollar project. The project is considered to be high risk since no similar projects have been undertaken before and there is no historical data. Some external stakeholders are reluctant to provide support.
What approach should the project manager take?

  1. Examine the plans, processes, policies, and knowledge that are specific to the organization undertaking the project
  2. Establish dialogue with stakeholders on the project constraints, assumptions, and critical inputs
  3. Convince senior management to close the project since the project lacks sponsorship and is considered to be high risk
  4. Host a project team meeting, then update the risk register and the project management plan

Answer(s): B



A project manager is assigned to a project in a company that is transitioning to agile. Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project. However, the project sponsor needs a quick win to ensure the continuation of the project.
What approach should the project manager use?

  1. An agile approach as this would provide working functionality earlier
  2. A predictive approach as this would please the senior stakeholders
  3. A hybrid project as this will mitigate stakeholders' concerns
  4. A predictive approach as this will show benefits for all stakeholders

Answer(s): C



A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task.
What should the project manager do to obtain the information required by the developer?

  1. Request direction from the project sponsor
  2. Write an email to the client requesting clarification
  3. Seek support from the development manager
  4. Work with the product owner to clarify the requirement

Answer(s): D



A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.
What should the project manager do to enhance project team effectiveness?

  1. Implement team colocation to improve communication
  2. Identify the root cause of communication issues
  3. Initiate daily communication of project progress
  4. Schedule a communications control board meeting

Answer(s): B



A team member misses a project meeting without it being approved and has been penalized as defined in the ground rules. This team member, as well as other team members, insist that it is the first time they have seen this rule regarding the project and they do not agree with the penalty.
What should the project manager have done to avoid this situation?

  1. Ensured the team charter was developed by the team members
  2. Ensured the team members are fully supportive of all decisions
  3. Distributed the project charter to all team members
  4. Used a charismatic leadership style

Answer(s): A