Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared. Management asks the project manager to move forward with the project without an approved project scope statement.
What should the project manager do next?

  1. Escalate the issue to the project sponsor and add it to the risk register
  2. Refuse to work on the project because management is not following standard project management practices
  3. Meet with management to explain the potential problems with running a project without a project scope statement
  4. Start the project with inputs from the project charter to save time

Answer(s): C



A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches.
What does the project manager need to do first in order to have good project performance?

  1. Coach those team members lacking hybrid knowledge to learn on the job.
  2. Change the team to include hybrid experts.
  3. Assess the required training per team member.
  4. Deliver hybrid training to all team members.

Answer(s): C



While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future. To avoid major problems in the future, the team recommends corrective actions that will require additional funds. The project is already struggling to stay on budget and has even used some of the contingency reserves.
What should the project manager do?

  1. Ask the product designer why the deviation was not considered in the design phase
  2. Report to the project sponsor that the product is working and the project is struggling with the budget
  3. Evaluate and initiate the change request process with the stakeholders
  4. Ask the quality team to discard the sample and test again with a new sample

Answer(s): C



A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again.
What should the project lead do next?

  1. Notify senior management of the issues, and have them review the importance of agreements with the team
  2. Challenge the team to determine if the issues surfaced again because agreements were not followed
  3. Post the agreements in a conspicuous place where all of the team members can see them
  4. Let the team self-organize and determine the best means to prevent the issues from occurring again

Answer(s): B



A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned. The SME asks the project manager to write, document and include it in the lessons learned register.
What should the project manager do?

  1. Assign the documenting task to a project team member.
  2. Ask the SME to document and capture the occurrence.
  3. Request the SME to wait until the project closure phase.
  4. Take ownership of documenting this information.

Answer(s): D