A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.
What should the project manager do next?

  1. Agree with the project team to modify and delete some of the stories in the current sprint backlog
  2. Obtain approval from the project team and add the new story to the product backlog
  3. Receive an agreement from the product owner and add the new story to the product backlog
  4. Negotiate with the scrum master before adding the new story to the sprint backlog

Answer(s): C



DRAG DROP (Drag and Drop is not supported).
A project manager in an automotive company is scheduling activities for a complex project. Some of the project requirements are fixed and some are flexible.
Match the items on the left with the methodology on the right that the project manager is using.
Select and Place:

  1. See Explanation section for answer.

Answer(s): A

Explanation:



A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.
Which two actions should the project manager leverage to ensure the team is meeting performance expectations? (Choose two.)

  1. Require a monthly individual status report
  2. Hold daily virtual meetings to review progress
  3. Utilize a web-based kanban board
  4. Task functional managers to drive accountability
  5. Implement time-keeping software for team members

Answer(s): B,C



An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.
What should the project lead recommend?

  1. Send weekly reports to the PMO, and use a kanban board for the product owner and the project team
  2. Send the weekly report to the PMO and the product owner, and use a kanban board for the project team
  3. Invite the PMO manager to the daily standup with the project team and product owner
  4. Send weekly reports to all stakeholders, including the project team and the product owner

Answer(s): A



An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).
What should the project lead do?

  1. Discuss the product owner's recommendations with the team and implement the agreed-on solutions
  2. Allow the team to self-organize so one of the resources can lead the team to achieve consensus
  3. Discuss the recommendations with the test manager and request better quality control
  4. Facilitate the meeting so anyone can share their ideas and is heard during the session

Answer(s): D