A company starts implementing Scrum. About halfway through the first sprint, communication issues develop. Some project team members are not in sync with other team members.What is the cause for this communication gap?
Answer(s): B
During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.How should the project manager handle this?
Answer(s): A
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints. However, the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion.What are two issues that these actions by the project manager could cause? (Choose two.)
Answer(s): B,E
A client is structured as a matrix organization for an agile project. The project manager is working on-site with key stakeholders from different parts of the organization.How should the project manager handle the different stakeholders?
A project manager is leading an in-house company project in its very early stages. This current project is similar to another project that ended a year ago.What should the project manager do to analyze the involved stakeholders?