Project Management Professional Questions 391–395 (page: 80)

Updated On: 10-Feb-2026

A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations. The project does not pass the financial threshold but is also expected to increase market share, improve customer services, and retain more customers. The project is planned as a phased implementation, building on learning from the retrospectives during each phase.
How should the business increase the value of the project?

  1. Ask the benefits owner to reassess the identified risks that are impacting the outcomes of the financial benefits.
  2. Use a fishbone diagram to find the root cause of the lower financial benefits with the benefits owner.
  3. Consult with experts on methods to reduce costs and increase the financial value of the project.
  4. Quantify the expected tangible and intangible benefits in the benefits management plan for each phase.

Answer(s): D



During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?

  1. Update the risk register and project log, and manage the budget closely.
  2. Revise the project scope accordingly to cope with the budget changes.
  3. Submit a change request to accelerate the project as requested.
  4. Ask upper management for more funds, and update the project budget.

Answer(s): A



FILL BLANK -
The following table shows the business value created and the development effort required to implement various features in a product.
Which feature should the team prioritize first? Enter the feature name in the box below.
______

  1. Option A
  2. Option B
  3. Option C
  4. Option D

Answer(s): A



An agile project is running activities to define the minimum viable product (MVP). During the session, the project manager identifies some mandatory regulations, but there is no consensus to include these regulations in the MVP because it may extend the duration of the project.
What should the project manager do?

  1. Ask the project sponsor to add more time to the project.
  2. Get commitment from the team to include all of the required regulations.
  3. Share with the participants the need to focus only on product functionality.
  4. Train the team on the new regulations as requested by management.

Answer(s): B



A project team has recently completed the initial sprint for developing an automated payroll system for a company. The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next.
Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two.)

  1. Company mission and vision
  2. Sprint goal
  3. Sprint charter
  4. Product backlog
  5. Burndown chart

Answer(s): B,D



Viewing page 80 of 285
Viewing questions 396 - 400 out of 2195 questions