Free PRINCE2-Foundation Exam Braindumps

Identify the missing word(s) from the following sentence. A project is a temporary organization that is created for the purpose of delivering one or more business products according to an agreed?

  1. Senior User
  2. Business Case
  3. Change
  4. Cost

Answer(s): B



Which is NOT a purpose of a Product Description?

  1. Define the time and cost needed to produce the product
  2. Define the quality skills required to check the product
  3. Define the function and appearance of the product
  4. Define the development skills required to produce the product

Answer(s): B



Which is a purpose of a Communication Management Strategy?

  1. Ensuring the project team can use the required reporting tools
  2. Producing reports for the Project Board
  3. Defining the communication method between the Project Board and corporate or programme management
  4. Ensuring stakeholders are aware of their responsibilities

Answer(s): C



Who is the key project decision-maker in the project management team?

  1. Corporate management
  2. Executive
  3. Change Authority
  4. Project Manager

Answer(s): B



Which regular report provides the Project Board with a summaryof stage status?

  1. Communication Management Strategy
  2. Project Brief
  3. Highlight Report
  4. Checkpoint Report

Answer(s): C