Free PRINCE2-Foundation Exam Braindumps (page: 3)

Page 2 of 182

What environment does PRINCE2 assume?

  1. Third party
  2. Customer/Supplier
  3. Fixed-price contract
  4. Management and Specialist

Answer(s): B



A characteristic of a project is that they come with an element of uncertainty. Which of the following PRINCE2 themes will help with the identification and management of such uncertainty?

  1. Quality
  2. Risk
  3. Change
  4. Organization

Answer(s): B



Which is a benefit of using PRINCE2?

  1. Stakeholders are kept out of planning and decision making
  2. Participants understand each other's roles and needs
  3. Stakeholders are not involved in assuring the project work
  4. All problems are escalated to all stakeholders

Answer(s): A



Which PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?

  1. Continued business justification
  2. Manage by exception
  3. Focus on products
  4. Manage by stages

Answer(s): D