Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

  1. Change
  2. Cross-functional
  3. Unique
  4. Risk

Answer(s): C

Explanation:

The characteristic of a project that reflects different perspectives and motivations for customers and suppliers is its "Unique" nature. Projects typically bring together diverse groups, each with distinct objectives and expectations. The uniqueness of a project involves these varied stakeholder inputs and requirements, which often need to be balanced and managed.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

  1. Manage by stages
  2. Manage by exception
  3. Continued business justification
  4. Learn from experience

Answer(s): B

Explanation:

The PRINCE2 principle supported by the setting of tolerances for the three levels of plan (Project, Stage, and Team Plans) is "Manage by exception." This principle allows management to set predefined tolerances for project objectives, and only escalate issues to higher management if these tolerances are exceeded, thereby facilitating efficient use of management time and focus.


Reference:

PRINCE2 Foundation manual, PRINCE2 official resources



Which role is responsible for creating Checkpoint Reports?

  1. Senior Supplier
  2. Team Manager
  3. Change Authority
  4. Project Support

Answer(s): B

Explanation:

In PRINCE2®, the Team Manager is responsible for creating Checkpoint Reports. These reports provide the Project Manager with a summary of the progress within a Work Package, detailing performance against plan, and highlighting any issues that might affect the work.


Reference:

PRINCE2® Foundation official study materials.



Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

  1. project cost tolerance
  2. stage cost tolerance
  3. Work Package cost tolerance
  4. product cost tolerance

Answer(s): C

Explanation:

A Project Manager agrees on the Work Package cost tolerances with a Team Manager. This agreement defines the acceptable cost variance within which the Team Manager can operate without needing further approval.


Reference:

PRINCE2® Foundation official study materials.