PRINCE2 FOUNDATION

A. Use of a particular set of technical skil s
B. Use of a specific set of Team Managers
C. An authorization from corporate or programme management
D. Commitment of resources

Answer(s): D
QUESTION: 89

In which product would a product's quality tolerance be defined?

A. Project Product Description
B. Product Description
C. Stage Plan
D. Quality Management Strategy

Answer(s): B
QUESTION: 90

Which of the following would the Project Board only authorize one at a time?

A. Work Packages
B. Stages
C. Team Plans
D. Product Description

Answer(s): B
QUESTION: 91

Which is NOT an objective of PRINCE2 stages?

A. Provide an opportunity to assess the project viability
B. Identify the necessary Work Packages
C. Al ow clarification of the impact of an external influence
D. Ensure that key decisions are made prior to work needed to implement them

Answer(s): B

QUESTION: 92
The Project Board needs to assess project viability at certain points as defined in the Project
Plan.
How does the Progress theme assist this?

A. Sending regular Checkpoint Reports
B. Authorizing one stage at a time
C. Creating Exception Reports when tolerances are threatened
D. Reports during project closure

Answer(s): B
QUESTION: 93


https://Free-Braindumps.com

Viewing page 20 of 160
Viewing questions 77 - 80 out of 500 questions


PRINCE2 Foundation Exam Discussions & Posts (Share your experience with others)

AI Tutor AI Tutor 👋 I’m here to help!