Which product would be updated to show that a decision has been made on an off-specification which has now been closed?

  1. Quality Register
  2. Daily Log
  3. Issue Report
  4. Risk Register

Answer(s): C



If a product's weight was specified to be 300 grams but could only be built to a weight of 400 grams, which of the following would be created?

  1. Exception Plan
  2. Request for change
  3. Off-specification
  4. Exception Report

Answer(s): C



What is a purpose of the Change theme?

  1. Prevent change to anything agreed in the Project Initiation Documentation
  2. Ensure any potential changes to baselined products are controlled
  3. Ensure that the correct versions are delivered to the customer
  4. Assess changes to only the specialist products

Answer(s): B



Which product confirms the version numbers of all products being developed within a given stage?

  1. Configuration Item Record
  2. Stage Plan
  3. Work Package
  4. Product Status Account

Answer(s): D



Identify the missing word from the following sentence... PRINCE2 uses the term [ ? ] to cover any relevant event that has happened, was not planned, and requires management action?

  1. Risk
  2. Change
  3. Issue
  4. Exception

Answer(s): C



According to PRINCE2, as well as holding informal problems/concerns, which product can also be used to record required actions or significant events not caught elsewhere?

  1. Daily Log
  2. Risk Register
  3. Issue Register
  4. Project notebook

Answer(s): A



Which option describes something that should be provided by the project, but currently is not (or is forecast not to be) provided?

  1. Problem/concern
  2. Concession
  3. Off-specification
  4. Exception Report

Answer(s): C



According to the Change theme, which of the following contains the steps of the recommended issue and change control procedure?

  1. Capture, Examine, Analyze Impact, Review Probability, Implement Action
  2. Capture, Log, Review, Resolve
  3. Assess, Decide, Escalate, Implement
  4. Capture, Examine, Propose, Decide, Implement

Answer(s): D