PRINCE2 PRINCE2-Foundation Exam Questions
PRINCE2 Foundation (Page 32 )

Updated On: 10-Mar-2026
PRINCE2 FOUNDATION
QUESTION: 143
Which of the following is FALSE regarding the Change theme?

A. Change control should be used to prevent changes being made to baselined products
B. Issues can affect the project's performance targets of time, cost, quality, scope, benefits and
risk
C. A pre-requisite of effective issue and change control would be an appropriate configuration
management system
D. Without issue and change control being applied, a project wil become unresponsive to its
stakeholders

Answer(s): A
QUESTION: 144

Who are allowed to raise an issue?

A. Only the Project Manager and Team Manager
B. Anyone with an interest in the project or its outcome
C. Only the Change Authority
D. Only members of the project management team

Answer(s): B
QUESTION: 145

Which product would be updated to show that a decision has been made on an off-specification
which has now been closed?

A. Quality Register
B. Daily Log
C. Issue Report
D. Risk Register

Answer(s): C
QUESTION: 146

If a product's weight was specified to be 300 grams but could only be built to a weight of 400
grams, which of the following would be created?

A. Exception Plan
B. Request for change
C. Off-specification
D. Exception Report

Answer(s): C
QUESTION: 147

What is a purpose of the Change theme?

A. Prevent change to anything agreed in the Project Initiation Documentation
B. Ensure any potential changes to baselined products are controlled
C. Ensure that the correct versions are delivered to the customer

https://Free-Braindumps.com

Viewing page 32 of 160
Viewing questions 125 - 128 out of 500 questions



Post your Comments and Discuss PRINCE2 PRINCE2-Foundation exam dumps with other Community members:

PRINCE2-Foundation Exam Discussions & Posts

AI Tutor