Which process would review the performance of the project against its baselines?

  1. Initiating a Project
  2. Closing a Project
  3. Managing Product Delivery
  4. Starting Up a Project

Answer(s): B



Which process provides an opportunity to ensure that all unachieved goals and objectives are identified?

  1. Initiating a Project
  2. Controlling a Stage
  3. Directing a Project
  4. Closing a Project

Answer(s): D



Which process ensures that provision has been made to address any open issues of risks, with follow-on action recommendations?

  1. Closing a Project
  2. Controlling a Stage
  3. Directing a Project
  4. Initiating a Project

Answer(s): A



What is a purpose of the Closing a Project process?

  1. Provide a fixed point at which acceptance for the project product is confirmed
  2. Enable the Project Board to review the success of the current stage
  3. Assign work to be done and monitor such work
  4. Enable the organization to understand the work that needs to be done to deliver the project's products

Answer(s): A



According to PRINCE2, which of the following statements is FALSE regarding project closure?

  1. A clear end to the project gives recognition that the original objectives have been met
  2. A clear end to the project provides an opportunity to ensure that all unachieved goals and objectives are identified
  3. A clear end to the project enables the organization to understand the work that needs to be done to deliver the project's products
  4. A clear end to the project transfers ownership of the products to the customer

Answer(s): C



Identify the missing word(s) in the following sentence... The purpose of the Closing a Project process is to provide a fixed point at which acceptance for the [?] is confirmed.

  1. Final project cost
  2. Project product
  3. Project scope
  4. Project mandate

Answer(s): B



If a Project Manager were to receive progress information on a Work Package during a stage, which one of the following products would the Project Manager update to show the progress that's been made?

  1. Checkpoint Report
  2. Stage Plan
  3. Benefits Review Plan
  4. Project Plan

Answer(s): B



In which situation might the Controlling a Stage process be used?

  1. Managing a long initiation stage of a complex project
  2. Managing the activities of a complex programme
  3. Managing support activities following the handover of the products to the operational environment
  4. Creating an Exception Plan to replace the current Stage Plan

Answer(s): A