Identify the missing word from the following sentence... PRINCE2 uses the term [ ? ] to cover any relevant event that has happened, was not planned, and requires management action?

  1. Risk
  2. Change
  3. Issue
  4. Exception

Answer(s): C



According to PRINCE2, as well as holding informal problems/concerns, which product can also be used to record required actions or significant events not caught elsewhere?

  1. Daily Log
  2. Risk Register
  3. Issue Register
  4. Project notebook

Answer(s): A



Which option describes something that should be provided by the project, but currently is not (or is forecast not to be) provided?

  1. Problem/concern
  2. Concession
  3. Off-specification
  4. Exception Report

Answer(s): C



According to the Change theme, which of the following contains the steps of the recommended issue and change control procedure?

  1. Capture, Examine, Analyze Impact, Review Probability, Implement Action
  2. Capture, Log, Review, Resolve
  3. Assess, Decide, Escalate, Implement
  4. Capture, Examine, Propose, Decide, Implement

Answer(s): D