Which product is used to inform the Project Board of a forecast deviation of stage-level tolerance?

  1. Exception Plan
  2. Exception Report
  3. Off-specification
  4. Highlight Report

Answer(s): B



To which role should a forecast breach of benefits tolerance be escalated?

  1. Project Manager
  2. Executive
  3. Senior User
  4. Corporate or programme management

Answer(s): D



Which theme has a purpose of providing the mechanisms to forecast the project's continued
viability?

  1. Risk
  2. Progress
  3. Plans
  4. Business Case

Answer(s): B



How does the Progress theme assist the Project Board to assess project viability at regular intervals?

  1. Sends regular Checkpoint Reports to the Project Board
  2. Only one management stage is authorized at a time
  3. Creates Exception Reports when tolerances are forecast to be exceeded
  4. Reports to the Project Board during project closure

Answer(s): B



What is a purpose of the Progress theme?

  1. Identify, assess and control uncertainty
  2. To establish mechanisms to monitor and control what has happened against what had been planned
  3. Facilitate communication and control by defining the means of delivering the products
  4. Define and implement the means by which the project will create and verify products which are fit for purpose

Answer(s): B



Are the following statements regarding technical stages true or false?
1. There can be more than one technical stage per management stage
2. The work can be grouped by the set of techniques used or the products created

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Both 1 and 2 are false

Answer(s): C



What factors need to be taken into consideration when identifying the number of management stages required?
1. Where key decisions points need to be
2. The amount of risk within the project
3. The number of technical stages
4. How confident the Project Board and Project Manager are with proceeding

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): B



The creation of an Exception Plan often follows which situation?

  1. A time or cost slippage occurs during a management stage
  2. An Exception Report being submitted to the Project Board
  3. A Stage Plan is updated due to an urgent corrective action being taken
  4. An Issue Report being created

Answer(s): B