What type of control is a report which is sent from the Team Manager to the Project Manager, at the intervals agreed in the Work Package?

  1. Event-driven
  2. Exception based
  3. Time-driven
  4. Ad-hoc

Answer(s): C



Which of the following is NOT within the authority of the Project Board?

  1. Trigger premature closure of the project
  2. Setting stage-level tolerance
  3. Authorizing initiation
  4. Continuation where project-level tolerance is forecast to be exceeded

Answer(s): D



Which of the following is a Project Board control?

  1. Approving a deviation of benefits tolerance
  2. Approve a Plan, with its relevant tolerances for the next management stage
  3. Review Checkpoint Reports to monitor progress
  4. Use of project registers and logs to review progress

Answer(s): B



Which level of management has control over a Work Package, as long as they are within the Work Package tolerances?

  1. Project Manager
  2. Project Board
  3. Team Manager
  4. Corporate or programme management

Answer(s): C



Which of the following describes the recommended minimum number of stages?

  1. Initiation as the first stage, the remainder of the project as the second stage
  2. Initiation as the first stage, closure activities as the second stage
  3. Procurement as the first stage, design and implementation as the second stage
  4. Pre-project work as the first stage, initiation as the second stage

Answer(s): A



Which of the following is mandatory in a PRINCE2 project?

  1. Use of a separate person as Team Manager
  2. Use of management stages
  3. Use of Exception Plans
  4. Use of Team Plans

Answer(s): B



Which management level uses the mechanisms included within the Progress theme to control any unacceptable deviations?

  1. Only the Project Board
  2. Only the Project Manager
  3. All levels of management
  4. Only corporate or programme management

Answer(s): C



What name is given to the permissible deviation allowed above and below a plan's target for time and cost without escalating the deviation to the next level of management?

  1. Concession
  2. Tolerance
  3. Project Issue
  4. Off-specification

Answer(s): B