Free PRINCE2 Foundation Exam Braindumps
PRINCE2 Foundation Questions 329–336 (page: 43)

Updated On: 10-Jul-2026

Are the following statements regarding raising exceptions true or false?
1. If the stage is forecast to exceed its tolerances, the Project Manager should produce an Issue Report to capture and analyze the details of the deviation
2. Where a Work Package is forecast to exceed its tolerances, the Project Manager may request the Team Manager to produce an Exception Plan

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Both 1 and 2 are false

Answer(s): A



Which product, produced by the Project Manager, would contain information on 'products completed during the period'?

  1. Product Status Account
  2. Checkpoint Report
  3. Highlight Report
  4. Exception Report

Answer(s): C



Which product would document any unfinished work, ongoing issues and risks?

  1. Project closure notification
  2. Lessons Report
  3. End Project Report
  4. Risk Register

Answer(s): C



What is produced by the Project Manager to define and keep control of the work to build products?

  1. Product Status Account
  2. Checkpoint Report
  3. Highlight Report
  4. Work Package

Answer(s): D



What is NOT a purpose of the End Stage Report?

  1. Allow the Project Board to decide what to do next with the project
  2. Help decide whether to amend the project scope, or stop the project
  3. Escalate a stage-level tolerance threat to the Project Board
  4. Give a summary of progress to date

Answer(s): C



What product is reviewed by the Project Manager as part of progress assessment to determine whether a Work Package is performing to the agreed cost and time tolerances?

  1. Highlight Report
  2. Checkpoint Report
  3. Exception Report
  4. Off-specification

Answer(s): B



Are the following statements regarding quality control true or false?
1. Includes identifying ways to eliminate causes of unsatisfactory performance
2. Involves defining the products required, their quality criteria and the relevant quality methods

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Both 1 and 2 are false

Answer(s): A



Once a product has been completed, from whom would the Team Manager get approval for its completion?

  1. Project Manager
  2. The authority defined in the product's Product Description
  3. Quality Assurance as part of their independent audits
  4. The producer of the product

Answer(s): B



Viewing page 43 of 92
Viewing questions 337 - 344 out of 724 questions


Post your Comments and Discuss PRINCE2 PRINCE2 Foundation exam prep with other Community members:

AI Tutor AI Tutor 👋 I’m here to help!