What is the first task of the product-based planning technique?

  1. Identify activities and dependencies
  2. Write Product Descriptions
  3. Create a product breakdown structure
  4. Write the Project Product Description

Answer(s): D



Which of the following statements are true regarding the product-based planning technique?
1. Product Descriptions show the hierarchy of a Plan's products
2. Identifying activities and dependencies is a key task of product-based planning

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Both 1 and 2 are false

Answer(s): D



Which of the following would help to define the project's products and show the sequence in which those products are to be created?

  1. Writing Product Descriptions
  2. Product-based planning technique
  3. Creating a product breakdown structure
  4. Writing a Project Product Description

Answer(s): B



Which theme includes the estimating of the effort required to develop the project's products?

  1. Plans
  2. Progress
  3. Business Case
  4. Organization

Answer(s): A



Which role would represent the interests of the people who will be operating the project's products?

  1. Senior Supplier
  2. Executive
  3. Change Authority
  4. Senior User

Answer(s): B



During project initiation, who determines the use of a Change Authority and whether a change budget will be used?

  1. Project Board
  2. Change Authority
  3. Project Manager
  4. Corporate or Programme Management

Answer(s): B



Which role is the key decision-maker on the project management team?

  1. Corporate or programme management
  2. Change Authority
  3. Project Manager
  4. Executive

Answer(s): D



Within the PRINCE2 customer/supplier environment, what is a supplier responsibility?

  1. Define what the acceptance criteria are for the project product
  2. Ensure the resources are made available to deliver the required result
  3. Secure the funding for the project
  4. Specify the desired project outcomes

Answer(s): B