Based on lessons from previous projects that used the ABC Company standard development model, the project board has set low cost and time tolerances for stage 2. As a result, the project manager plans to set very low tolerances for time and cost for all work packages to be carried out during stage 2.
Is this an appropriate application of the „manage by exception‟ principle, and why?

  1. Yes, because the project manager should set tolerance equally for all work packages in a stage.
  2. Yes, because setting appropriate tolerances for work packages will help keep the stage within tolerances.
  3. No, because tolerances set by the project manager should be the same as those set by the project board.
  4. No, because the project manager should divide the stage tolerances between the team managers.

Answer(s): B



View Related Case Study

During stage 4, a work package was authorized for the „delivered pilot courses‟ to be completed by the end of week 2. The „finalized materials‟ work package will start in week 3. Both work packages have zero tolerances, and finalizing the materials is dependent on feedback from the pilot courses. During week 1, there were some problems with the pilot courses, so at the start of week 2 the team manager rescheduled the courses to week 3, and reported this in the weekly checkpoint report as the end of week 2.
Should the team manager have reported this delay previously as an issue, and why?

  1. Yes, because the work package to deliver the pilot courses was forecast to exceed its time tolerance.
  2. Yes, because a team manager should not change the scheduled order of a work package.
  3. No, because the checkpoint report for week 1 should include information on any issues that occurred.
  4. No, because the feedback from the rescheduled courses can be used in week 4 to finalize the materials.

Answer(s): C



View Related Case Study

The project is now closed. The expected increase in revenue is not being achieved. It has been agreed with the team manager for the “marketing materials” that additional marketing activities will be undertaken to achieve the expected increase in revenue. Who should be responsible for monitoring the results of the marketing activities, and why?

  1. Senior user, because this person is responsible for realizing the benefits post-project.
  2. Senior user, because this person is responsible for specifying the desired from the project.
  3. The team manager for the „marketing materials‟, because this person has the skills to demonstrate that the activities are effective.
  4. The team manager for the „marketing materials‟, because the project board is disbanded at the end of the project.

Answer(s): A



View Related Case Study

MANAGING A STAGE BOUNDARY
The ABC Company trainers have been accredited and the course booking procedures have been amended. The „managing a stage boundary‟ process is taking place at the end of stage 3.
Which activity should occur during the „update the business case‟ activity?

  1. Update the overall plan with the time and cost taken to develop the „e-learning course‟ and „amended course booking procedures‟
  2. Break the „planned pilot courses‟ down into component products in order to identify the work required to deliver them.
  3. Review whether the possible sales of the training course to external companies are likely to cover the project costs.
  4. Review whether a new team manager should be appointed to lead the delivery of the pilot courses during stage 4.

Answer(s): A



Page 1 of 71



Post your Comments and Discuss PRINCE2 PRINCE2 PRACTITIONER exam with other Community members:

Marwin commented on July 30, 2024
The (NCP-MCI) 6.5 questions and answers are valid. I am very thankful for this reviewer; I passed the exam with a score of over 4000 on July 21, 2024.
UNITED STATES
upvote

Abdelrahman commented on July 21, 2024
Senarios senarios .. need alot of efforts
JORDAN
upvote

Jag commented on June 27, 2024
Thank you for providing this reliable and relevant exam guide. The communication with your support team was great. I appreciate your honesty.
UNITED KINGDOM
upvote

Blitz1 commented on May 25, 2024
q66 should be A. user should first login to a workstation , change their pass and then login to PC.
ROMANIA
upvote

Blitz1 commented on May 25, 2024
Q28 should be CD ( data drive and AOS) as per https://portal.nutanix.com/page/documents/kbs/details?targetId=kA00e000000LKMKCA4
ROMANIA
upvote

Blitz1 commented on May 24, 2024
q21 should be D Isolating Backplane Traffic by using VLANs (Logical Segmentation) You can separate management traffic from storage replication (or backplane) traffic by creating a separate network segment (LAN) for storage replication. For more information about the types of traffic seen on the management plane and the backplane https://portal.nutanix.com/page/documents/details?targetId=Nutanix-Security-Guide-v6_8:wc-network-segmentation-intro-wc-c.html
ROMANIA
upvote

Blitz1 commented on May 24, 2024
Q12 should be D. Prism Central applies storage policies to Categories. You need to tag the VMs and VGs in Categories. You might also attach VGs to VMs. When you apply different storage policies through different categories to a VG and VM tagged to each other, the storage policies are applied independently. The storage policy applied to the tagged VG does not affect the tagged VM and vice versa. https://portal.nutanix.com/page/documents/details?targetId=Prism-Central-Guide-vpc_2024_1:mul-cluster-storage-policy-pc-c.html
ROMANIA
upvote

elloco commented on May 22, 2024
nice dumps very helpful
MEXICO
upvote

Gabriel commented on May 04, 2024
This Dump worked. Pass my PM exam!!! I am CERTIFIED NOW! :-)
UNITED KINGDOM
upvote

Dimpho commented on April 02, 2024
very informative senario and relevent exam question
BOTSWANA
upvote

Jerad commented on March 21, 2024
Questions are valid in Europe. I passed this exam today with a 82% mark.
FRANCE
upvote

Anonymous commented on February 16, 2024
Q6 should be A https://portal.nutanix.com/page/documents/kbs/details?targetId=kA00e000000LUKeCAO#:~:text=Dedup%20and%20EC%20are%20not%20supported%20for%20RF1,RF1%20container%20does%20not%20support%20increasing%20replication%20factor.
QATAR
upvote

juliet commented on February 12, 2024
Is this for Prince2 v6 or v7 ?
UNITED KINGDOM
upvote

Regor commented on December 04, 2023
is this a valid prince2 practitioner dumps?
UNITED KINGDOM
upvote

Sandeep commented on July 25, 2022
the questiosn from this braindumps are same as in the real exam. my passing mark was 84%.
INDIA
upvote

Anil commented on July 18, 2023
nice questions
Anonymous
upvote

Agathenta commented on December 16, 2023
q35 should be a
Anonymous
upvote

Isak commented on July 06, 2023
i need it very much please share it in the fastest time.
Anonymous
upvote

User commented on August 29, 2023
only the free dumps will be enough for pass, or have to purchase the premium one. please suggest.
Anonymous
upvote

quen commented on July 26, 2023
please upload apache spark dumps
Anonymous
upvote

Erineo commented on November 02, 2023
q14 is b&c to reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but i see this as a part of the daily digest adjustment
Anonymous
upvote

Ann commented on September 15, 2023
hi can you please upload the dumps for sap contingent module. thanks
AUSTRALIA
upvote

Andrus commented on December 17, 2023
q52 should be d. vm storage controller bandwidth represents the amount of data (in terms of bandwidth) that a vms storage controller is using to read and write data to the storage fabric.
Anonymous
upvote

Andrus commented on December 17, 2023
Q52 should be D. VM Storage Controller Bandwidth represents the amount of data (in terms of bandwidth) that a VM's storage controller is using to read and write data to the storage fabric.
Anonymous
upvote

Agathenta commented on December 16, 2023
Q35 Should be A
Anonymous
upvote

Ezekiel commented on December 16, 2023
Question 27 should be C. Images are often associated with categories, and the clusters need to be added to the correct category to access those images.
Anonymous
upvote

Regor commented on December 04, 2023
Is this a valid Prince2 Practitioner dumps?
UNITED KINGDOM
upvote

Sanja commented on November 07, 2023
Looks helpful
Anonymous
upvote

Erineo commented on November 02, 2023
Q 28 is C&D explained in https://portal.nutanix.com/page/documents/kbs/details?targetId=kA00e000000LKMKCA4
Anonymous
upvote

Erineo commented on November 02, 2023
Q14 is B&C To reduce you will switch off mail for every single alert and you will switch on daily digest to get a mail once per day, you might even skip the empty digest mail but I see this as a part of the daily digest adjustment
Anonymous
upvote

Erineo commented on November 02, 2023
Q80, correct answer is A Nutanix AHV assigns an IP address from the address pool when it creates a managed VM NIC; the address releases back to the pool when the VM NIC or VM is deleted. With a managed network, AHV intercepts DHCP requests from guest VMs and bypasses traditional network-based DHCP servers. AHV uses the last network IP address in the assigned network for the managed network DHCP server unless you select Override DHCP server when you create the network.
Anonymous
upvote

Krat commented on September 30, 2023
Could you please upload the examen?
Anonymous
upvote

Ann commented on September 15, 2023
Hi can you please upload the dumps for SAP contingent module. Thanks
AUSTRALIA
upvote

Scott commented on September 08, 2023
that is awesome
UNITED STATES
upvote