One of the reasons a project life cycle is split into phases is to:

  1. facilitate formal go/no-go decision making during the project.
  2. balance the costs of work in each phase of project development.
  3. mirror the major deployments of resources throughout the project.
  4. chunk work into time periods of similar durations.

Answer(s): A



Which of the following best describes a project environment?

  1. The type of organisation concerned with implementation.
  2. The structured method used to control the project.
  3. The context within which a project is undertaken.
  4. An understanding of the risks involved in the project.

Answer(s): C



Which one of the following statements best describes a project?

  1. A project is a set of tools and techniques often used when delivering organisational change.
  2. A project is the sum of activities needed to remove uncertainty from a unique piece of work.
  3. A unique transient endeavour undertaken to achieve a desired outcome.
  4. A project is a method of planning work.

Answer(s): C



The document that identifies what information needs to be shared, to whom, why, when and how is called the:

  1. communication management plan.
  2. stakeholder mapping grid.
  3. document distribution schedule.
  4. responsibility assignment matrix.

Answer(s): A



An important aim of a post-project review is to:

  1. validate overall progress to date against the budget and schedule.
  2. capture learning and document it for future usage.
  3. ensure acceptance of all permanent documentation, signed by the sponsor.
  4. establish that project benefits have been identified.

Answer(s): B