The process that evaluates overall project performance to provide confidence is called:

  1. quality assurance.
  2. quality planning.
  3. quality control.
  4. quality audit.

Answer(s): A



Which one of the following statements about the project risk register is false?

  1. It facilitates the review and monitoring of risks.
  2. It facilitates the risk appetite.
  3. It facilitates the recording of risk responses.
  4. It facilitates the recording of risks.

Answer(s): B



Once a change has been requested what is the next step in the change control process?

  1. Evaluate the change.
  2. Advise the sponsor.
  3. Update the change log.
  4. Update the project plan.

Answer(s): A



A Responsibility Assignment Matrix (RAM) can be used to:

  1. define the terms of reference of the project manager.
  2. define the limits of the project sponsor's responsibilities.
  3. allocate risk management response activities to project personnel.
  4. allocate work packages to those responsible for project work.

Answer(s): D



An Organisational Breakdown Structure (OBS) is used to identify:

  1. the reporting structure and current availability of all individuals in the project.
  2. technical ability and line of communication for all individuals in the project.
  3. lines of communication and responsibility for all the individual managers in the project.
  4. the reporting structure and lines of communication for all individuals in the projects.

Answer(s): D