Close out documentation is initially discussed in which of the following meetings?

  1. Prime Contractor and Subcontractor Meetings
  2. Kickoff Meeting
  3. Weekly Progress Meetings
  4. Vendor Meeting

Answer(s): A



An ICT distribution designer installed a 50/1 ?5 mm/1300 nm fiber optic cable from Building A to identical Building B with a distance of 600 m (1968 ft) At Building B. the designer fusion splice this new cable to an existing identical 50/126 mm fiber optic cable that runs 800 m (2525 ft) to Building A. Both ends are terminated with SC connectors.
What is the loss budget for the above fiber link?

  1. 2.95 dB
  2. 3.40dB
  3. 3.90 dB
  4. 4.35 dB

Answer(s): C



In order for an ICT distribution designer to identify the BEST solutions for the client's needs they may have to provide

  1. Operation and Maintenance manuals
  2. subcontractors lists
  3. material lists (e.g., BOM).
  4. shop drawings

Answer(s): C



What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)

  1. 305 mm(12 in)
  2. 610 mm (24 in)
  3. 914 mm (36 in)
  4. 1270 mm (50 in)
  5. Below the area's 50-year frost line

Answer(s): B,E