A non-profit organization launched a program to reduce its dependence on regularly decreasing government funding sources. This program's goal was (o raise 50 percent of its operating expenses by selling its services to the for-profit sector. After three years, the goal was reached, deemed complete, and transitioned to operations. Eighteen months later, the organization discovers that its dependence on government funds has now increased to 80 percent, even though its operating budget has largely stayed the same
What should the program manager have done to avoid the issue of program benefits being unrealized after more than a year of implementation?

  1. Developed program transition and benefits sustainment plans as part of the transition to operations
  2. Had the operations manager follow the benefits management plan
  3. Worked with the operations department after the program was transitioned
  4. Completed the program a year earlier

Answer(s): A



A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects.
Where should the program manager incorporate this input?

  1. Program management plan
  2. Stakeholder register
  3. Vendor management matrix
  4. Program risk management plan

Answer(s): A



A critical program for a company fails lo delivers its intended benefits. The CEO and program sponsor are both held accountable and. ultimately, their employment is terminated by the board of directors What should the program manager do before formally closing the program?

  1. Update the benefits register
  2. Establish a program management information system (PMIS)
  3. Share lessons learned with an program team members
  4. Transfer all program documentation to the deputy program manager

Answer(s): C



The chief executive officer (CEO) informs the program manager that the delivery dale for protect A must be compressed by two months to accommodate market needs Project A relies upon deliverables from projects B and C.
Which of the following should the program manager do first?

  1. Direct the three project managers to crash their projects to allow project A the two months of scheduling needed
  2. Review the program resource management plan with the three project managers emphasizing their critical paths and shared critical resources to understand the possibility of accelerating the schedule
  3. Convene the change board to evaluate the cost benefit of the compression and the impact on the overall program
  4. Engage the executive sponsor and program board to evaluate the CEO's request and determine if the project manager should act on it

Answer(s): B



A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?

  1. Attitude about the program external political position and technical expertise
  2. Level of influence and participation and attitude about the program
  3. Expectation of program benefits, level of influence, and organizational culture
  4. Level of support/opposition technical expertise, and organizational culture

Answer(s): B