Throughout a multiyear program, component projects are transitioned to the customer. During the project acceptance phase, a potential risk is identified and brought to the program team's attention.What should be done with the identified potential risk?
Answer(s): A
The program sponsor returns from a board of directors meeting alter identifying a significant risk to the program schedule. This may Impact the program's benefits realization What should the program manager do next?
Answer(s): D
The customer of a three-year program does not want to receive any intermediate details on the program. The program appears to be in trouble and the customer is concerned about a new system's cost. The program manager has provided monthly performance reports throughout the program's lite cycle.Which of the following would the customer be interested in reviewing?
Answer(s): B
A biometrics firm has a facial recognition program with multiple components and project managers The project manager from the mobile device division escalates a vendor-related risk to the program manager After assessing the risk, the program manager determines that this risk may impact other projects within the program. However, this risk has a low degree of Impact and probability of occurringWhat should the program manager do first?
A program manager is concerned that a program will be unable to achieve its intended benefits. Howshould the program manager handle this concern?