Free ISEB-PM1 Exam Braindumps (page: 17)

Page 16 of 157

A team member is not performing well on the project because she is inexperienced in system development work. There is no one else available who is better qualified to do the work.
What is the BEST solution for the project manager?

  1. Consult with the functional manager to determine project completion incentives for the team member.
  2. Obtain a new resource more skilled in development work.
  3. Arrange for the team member to get training.
  4. Allocate some of the project schedule reserve.

Answer(s): C



The management theory that all people can direct their own efforts is:

  1. Theory Y.
  2. Herzberg's theory.
  3. Maslow's hierarchy.
  4. Theory X.

Answer(s): A



A project team member has been having a big disagreement with another team member for over two months when the other team members become involved. The issues are complex, but you have specific experience in the area and know what needs to be done. The BEST choice would be to:

  1. Make the decision yourself.
  2. Strive for fair resolution of the issue.
  3. Ask the other team members to stay out of the issue.
  4. Bring the team together and work out the issue to a win-win solution.

Answer(s): B



While creating the agenda for a status meeting with the team, a project manager receives input from one team member that an item should be added. Another team member says the team is not ready to resolve the item during the meeting. After much discussion, the project manager decides to put the item on the agenda as an initial discussion item only.
Which conflict resolution technique is the project manager using?

  1. Compromise
  2. Smoothing
  3. Forcing
  4. Withdrawal

Answer(s): A






Post your Comments and Discuss ITIL® ISEB-PM1 exam with other Community members: