Who has the responsibility of maintaining subcontractor contracts in SAP?

  1. Logistics coordinator.
  2. Project controller.
  3. Customer business controller.
  4. Cost and progress manager.

Answer(s): D



The one documentthat should always be used to identify and mitigate risk is the:

  1. risk management plan.
  2. scope statement.
  3. project charter.
  4. contingency plan.

Answer(s): A



When a Customer Contract is not yet signed and a purchase order has not yet been received, in which circumstances can a service be subcontracted?

  1. If the value of the purchase order does not exceed the approved cost baseline.
  2. If an early ramp-up project (ERP) is approved.
  3. Ifthe subcontractor agrees to receive their PO later, after the customer PO is issued.
  4. Ifthere is a formal approval from the Project Nlanager.

Answer(s): B



Internal acceptance is a milestone thatwill trigger:

  1. SAP billing block released.
  2. SAP goods receipt.
  3. customer invoicing.
  4. cost estimate to complete (ETC).

Answer(s): B