Which of the following Plans are approved by the Project Manager?

  1. Project Plan
  2. Team Plan
  3. Exception Plan
  4. Stage Plan

Answer(s): B



Identify the missing word(s) in the following sentence... The [?] is used by the Project Manager to capture and maintain information on all of the identified threats and opportunities relating to the project.

  1. Risk Register
  2. Risk Management Strategy
  3. Issue Register
  4. Risk owner

Answer(s): A



Which of the following would NOT be classified as a threat to a project?

  1. A competitor may launch a rival product first thus affecting the expected market share for the product
  2. It is possible that the product completes user acceptance testing in a single test cycle rather that the scheduled two
  3. A prototype may be damaged in transit
  4. A critical meeting could be affected by air travel disruption

Answer(s): B



Which of the following is NOT a purpose of the Risk theme?

  1. Improve the ability of the project to succeed
  2. To support better decision making
  3. To verify products are fit for purpose
  4. To assess uncertainty

Answer(s): C