PRINCE2 PRINCE2 Foundation Exam Questions
PRINCE2 Foundation 7 Edition (Page 19 )

Updated On: 12-May-2026
PRINCE2 FOUNDATION
B. Stakeholder's needs
C. Project objectives
D. Quality criteria of each product

Answer(s): C
QUESTION: 84

What is used to pass responsibility to a Team Manager for the production of one or more
products?

A. Exception Plan
B. Work Package
C. Product Description
D. Checkpoint Report

Answer(s): B
QUESTION: 85

Which of the following is used to inform the Project Board of a forecast deviation of stage-level
tolerance?

A. Exception Plan
B. Exception Report
C. Off-specification
D. Lessons Report

Answer(s): B
QUESTION: 86

To which role should a forecast breach of benefits tolerance be referred?

A. Project Manager
B. Executive
C. Senior Supplier
D. Corporate or programme management

Answer(s): D
QUESTION: 87

Which is NOT an event-driven control?

A. Highlight Report
B. Exception Report
C. Project Initiation Documentation
D. End of a stage

Answer(s): A
QUESTION: 88

Identify the missing words in the following sentence... PRINCE2 management stages equate to
[?], which is a factor that differentiates them from technical stages

https://Free-Braindumps.com

Viewing page 19 of 160
Viewing questions 73 - 76 out of 500 questions