What is the purpose of the Risk Management Strategy?

  1. Describes in detail each risk identified in the project and how each risk should be managed
  2. Describes how each risk owner and risk actionee will manage and fund the actions to mitigate each risk
  3. Describes the risk response actions taken to mitigate the project's risks
  4. Describes the techniques and standards to be applied and responsibilities for achieving effective risk management procedures

Answer(s): D



Which of the following products is used after the Starting Up a Project process to capture and maintain information on all of the identified threats and opportunities relating to the project?

  1. Risk Management Strategy
  2. Risk Register
  3. Issue Register
  4. Quality Register

Answer(s): B



Which of the following risk responses can be used to seize an opportunity to ensure a risk 'will' happen and the impact 'will' be realized?

  1. Accept
  2. Exploit
  3. Enhance
  4. Fallback

Answer(s): B



What is the name given to an individual who is responsible for the management, monitoring and control of all aspects of a particular risk assigned to them?

  1. Risk Actionee
  2. Risk Coordinator
  3. Project Risk Manager
  4. Risk Owner

Answer(s): D