Which of the following represents the threshold levels of risk exposure that, when exceeded, will trigger an Exception Report?

  1. Risk proximity
  2. Risk tolerance
  3. Risk allowance
  4. Risk profile

Answer(s): B



Which of the following statements describes a risk cause?

  1. The area of uncertainty in terms of the threat or the opportunity
  2. The situation that gives rise to the risk
  3. The impact(s) that the risk would have on the project objectives should the risk materialize
  4. How soon in the future the risk is likely to occur

Answer(s): B



Which of the following statements describes a risk event?

  1. The area of uncertainty in terms of the threat or the opportunity
  2. The situation that gives rise to the risk
  3. The impact(s) that the risk would have on the project objectives should the risk materialize
  4. How soon in the future the risk is likely to occur

Answer(s): A



Which of the following statements describes a risk effect?

  1. The area of uncertainty in terms of the threat or the opportunity
  2. The situation that gives rise to the risk
  3. The impact(s) that the risk would have on the project objectives should the risk materialize
  4. How soon in the future the risk is likely to occur

Answer(s): C