What is a purpose of a Daily Log?

A. Record the products and activities planned for the stage
B. Record actions taken to recover from issues NOT recorded in the Issue Register
C. Record and track the status of all products produced during a stage
D. Provide a regular update to the Project Board on the progress of the stage

Answer(s): B
QUESTION: 94

The purpose of the Progress theme is to do which of the following?

A. Identify, assess and control uncertainty
B. To establish mechanisms to monitor and control what has happened against what is planned
C. Facilitate communication and control by defining the means of delivering the products
D. Define and implement the means by which the project wil create and verify products which
are fit for purpose

Answer(s): B
QUESTION: 95

Which of the following statements are correct regarding the use of management stages?
1. Provide review and decision points
2. Enable key decisions to be made prior to the detailed work
3. Facilitate the manage by exception principle
4. Enables the project manager to have complete autonomy over the products to be produced

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4

Answer(s): A
QUESTION: 96

Which of the following are correct regarding the definition of a technical stage?
1. Technical stages never overlap
2. They are typified by the use of a particular set of specialist skil s
3. Cover elements such as design, build and implementation
4. The work can be grouped by the set of techniques used

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4

Answer(s): D
QUESTION: 97

Which of the following are factors that need to be taken into consideration when identifying
management stages?

https://Free-Braindumps.com

Viewing page 21 of 160
Viewing questions 81 - 84 out of 500 questions


PRINCE2 Foundation Exam Discussions & Posts (Share your experience with others)

AI Tutor AI Tutor 👋 I’m here to help!