PRINCE2 PRINCE2-Foundation Exam Questions
PRINCE2 Foundation (Page 23 )

Updated On: 10-Mar-2026
PRINCE2 FOUNDATION
Answer(s): B
QUESTION: 102

Which level of management in the project management team has the ability to review progress
and decide whether to continue, change or stop the project?

A. Project Manager
B. Project Board
C. Team Manager
D. Corporate or programme management

Answer(s): B
QUESTION: 103

There should be at least two management stages in a PRINCE2 project. Which of the following
options describes those stages?

A. Initiation as the first stage, the remainder of the project as the second stage
B. Initiation as the first stage, closure activities as the second stage
C. Procurement as the first stage, design and implementation as the second stage
D. Pre-project work as the first stage, initiation as the second stage

Answer(s): A
QUESTION: 104

Please refer to section 10.3.2.1 in the PRINCE2 Manual. (Exception Plans are only produced if
requested by the Project Board. Team Plans and the use of seperate people as Team
Managers are optional in PRINCE2)

A. Use of Team Managers
B. Use of management stages
C. Use of Exception Plans
D. Use of Team Plans

Answer(s): B
QUESTION: 105

The Project Board have overall control at what level?

A. Day-to-day control for a management stage within stage tolerance
B. Work Package level within Work Package tolerance
C. Project level within project tolerance
D. Al levels of plans and tolerances

Answer(s): C
QUESTION: 106

What name is given to the permissible deviation al owed above and below a plan's target for
time and cost without escalating the deviation to the next level of management?

A. Concession

https://Free-Braindumps.com

Viewing page 23 of 160
Viewing questions 89 - 92 out of 500 questions