According to PRINCE2, it is seldom desirable, or possible, to plan an entire project in detail at the start. Which one of the following is given as a reason for this?

  1. It can be difficult to predict the actual performance of resources
  2. All aspects of planning become more difficult the further into the future they extend
  3. Sufficient detail is only known once the relevant stage has begun
  4. The supplier is unlikely to comprehend the detailed schedule

Answer(s): B



Why does PRINCE2 recommend having three levels of plan?

  1. The more levels there are, the more stable the plan detail will become
  2. Aspects of planning become more difficult the further into the future they extend
  3. To reflect that there are 3 key stakeholder project interests
  4. To reflect the needs of the different levels of management involved in the project, stage and team

Answer(s): D



Which of the following Plans can be approved by the Project Manager?

  1. Project Plan
  2. Team Plan
  3. Exception Plan at stage-level
  4. Stage Plan

Answer(s): B



In which process is it decided that an Exception Plan should be created to replace a Stage Plan?

  1. Directing a Project
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Closing a Project

Answer(s): A



Which product identifies the source products from which a product is to be derived?

  1. Product Breakdown Structure
  2. Product checklist
  3. Product Description
  4. Project approach

Answer(s): C



Which PRINCE2 theme has a purpose to facilitate communication and control by defining the means of delivering the products?

  1. Plans
  2. Progress
  3. Organization
  4. Change

Answer(s): A



Identify the missing word(s) in the following sentence... The development and maintenance of a credible [?] provides a baseline against which progress can be measured.

  1. Product
  2. Product Status Account
  3. Business Case
  4. Plan

Answer(s): D



Which of the following would define the sequence in which the products are to be created and any dependencies between them?

  1. Product Status Account
  2. Product flow diagram
  3. Product breakdown structure
  4. Product Description

Answer(s): B



Viewing page 24 of 92
Viewing questions 185 - 192 out of 724 questions