In which product would a product's quality tolerance be defined?

  1. Project Product Description
  2. Product Description
  3. Stage Plan
  4. Quality Management Strategy

Answer(s): B



Which of the following would the Project Board only authorize one at a time?

  1. Work Packages
  2. Stages
  3. Team Plans
  4. Product Description

Answer(s): B



Which is NOT an objective of PRINCE2 stages?

  1. Provide an opportunity to assess the project viability
  2. Identify the necessary Work Packages
  3. Allow clarification of the impact of an external influence
  4. Ensure that key decisions are made prior to work needed to implement them

Answer(s): B



The Project Board needs to assess project viability at certain points as defined in the Project Plan.
How does the Progress theme assist this?

  1. Sending regular Checkpoint Reports
  2. Authorizing one stage at a time
  3. Creating Exception Reports when tolerances are threatened
  4. Reports during project closure

Answer(s): B