Which of the following are factors that need to be taken into consideration when identifying management stages?
1. Where the key decisions points need to be
2. The amount of risk within the project
3. The number of technical stages
4. How confident the Project Board and Project Manager are with proceeding

  1. 1, 2, 3
  2. 1, 2, 4
  3. 1, 3, 4
  4. 2, 3, 4

Answer(s): B



The creation of an Exception Plan often follows which of the following situations?

  1. A time or cost slippage occurring during a management stage
  2. An Exception Report being submitted to the Project Board in the case of a management stage being forecast to exceed its tolerance
  3. A Stage Plan updated due to an urgent corrective action being taken by the Project Manager
  4. A newly identified risk being captured and documented in the Risk Register

Answer(s): B



What type of progress control is a Checkpoint Report?

  1. Event-driven
  2. Exception-based
  3. Time-driven
  4. Ad hoc-based

Answer(s): C



Which of the following is NOT within the authority of the Project Board?

  1. Approve the End Project Report
  2. Set Stage-level tolerance
  3. Approve Stage Plans
  4. Set project-level tolerance

Answer(s): D